Core Purpose

The Ministry of Power confers powers under Section 164 of the Electricity Act, 2003, on M/s Torrent Solar Power Private Limited for laying an overhead transmission line connecting its proposed renewable energy power project in Osmanabad, Maharashtra, granting it powers equivalent to a telegraph authority under the Indian Telegraph Act, 1885.

Detailed Summary

This order (S.O. 4340(E), dated 4 October 2024) issued by the Ministry of Power authorizes M/s Torrent Solar Power Private Limited (registered office "Samanvay", 600 Tapovan, Ambavadi, Ahmedabad, Gujarat) under Section 164 of the Electricity Act, 2003, conferring the powers of a telegraph authority under the Indian Telegraph Act, 1885, to lay a dedicated overhead transmission line providing connectivity to its proposed RE (renewable energy) power project in Osmanabad, Maharashtra. Prior approval under Section 68(1) of the Electricity Act, 2003 was granted by the Ministry vide File No. 25-17/7/2024-PG dated 16 February 2024. Public notice was published in The Times of India, Lokmat Samachar and Punyanagari (all dated 24 April 2024) and in the Weekly Gazette of India dated 25 May 2024; the applicant's affidavit dated 1 August 2024 confirmed no observations were received within two months. The transmission line passes through villages in Kaij and Bid tehsils of Bid district, and Wasi (Washi) tehsil of Usmanabad (Osmanabad) district, Maharashtra, including Nandur Ghat, Pithi Ghat, Vaijala, Borkhed and Fakrabad among others. The 25-year authorization carries standard conditions including consent of local bodies, Railways and Highway authorities, compliance with Appropriate Commission regulations, Electrical Inspector approval, submission of Civil Aviation/Defence clearances, and compliance with Supreme Court orders in Petition No. 838 of 2019 concerning the Great Indian Bustard. Issued under File No. 25-16/37/2024-PG and signed by M.V.N. Vara Prasad, Under Secretary (PG).

Full Text

CG-DL-E-07102024-257732 EXTRAORDINARY PART II—Section 3—Sub-section (ii) 6450 GI/2024 (1) MINISTRY OF POWER ORDER New Delhi, the 4th October, 2024 S.O. 4340(E).—Whereas M/s Torrent Solar Power Private Limited, the applicant with its registered office at "Samanvay", 600, Tapovan, Ambavadi, Ahmedabad-380015 (Gujarat)” India, has applied for authorization under Section 164 of the Electricity Act, 2003 for laying of dedicated overhead transmission line included in the transmission system for providing Connectivity for its proposed RE Power Project in Osmanabad, Maharashtra. And whereas Ministry of Power, Government of India vide its File No. 25-17/7/2024-PG dated 16.02.2024 had granted prior approval under section 68(1) of the Electricity Act, 2003 for laying of dedicated overhead transmission line included in the transmission system for providing connectivity to M/s Torrent Solar Power Private Limited for its proposed RE Power Project in Osmanabad, Maharashtra. M/s Torrent Solar Power Private Limited had published notice for transmission scheme in local newspapers The Times of India (in English) dated 24.04.2024, Lokmat Samachar (in Hindi) dated 24.04.2024 Punyanagari (in Marathi) dated 24.04.2024, and in Weekly Gazette of India dated 25.05.2024 for the general public to make observations/representations on the proposed transmission route within two months from the date of publication. Subsequently, M/s Torrent Solar Power Private Limited has submitted an affidavit dated 01.08.2024 declaring that no observation/representation was received within two months from the date of Publication in the official Gazette of Government of India. And now the applicant has requested to confer upon him, all the powers under section 164 of the Electricity Act, 2003, which the telegraph authority possess under the Indian Telegraph Act, 1885 with respect to the placing of telegraph lines and posts for the purpose of a telegraph established or maintained by Government or to be so established or maintained for laying of dedicated overhead transmission line for providing Connectivity to M/s Torrent Solar Power Private Limited for its proposed RE Power Project in Osmanabad, Maharashtra. The following overhead transmission line is covered under this scheme: The overhead transmission line covered under the above scheme will pass through, over, around and between the following villages, towns and cities of Maharashtra: | Villages | Tehsil | District | State | |---|---|---|---| | Nandur Ghat, Pithi Ghat, Khomanwadi | Kaij | Bid | Maharashtra | | Fakrabad, Dongarwadi, Para, Singewadi, Selu, Sarola Mandwa, Pimpalgaon Kothala | Wasi | Usmanabad | Maharashtra | | Villages | Tehsil | District | State | |---|---|---|---| | Vaijala, Pachegaon | Patoda | Bid | Maharashtra | | Borkhed, Wadwadi, Loni, Sultanpur, Khadki, Tandulwadi, Savi, Dhotra, Hingnibuzurg, Andapuri, Kumbhari, Murshidpur, Chandegaon, Chandniwadi, Satra, Pimpri, Anjanwati, Ghargaon, Golangri, Kanedi, Chausala, Raulasgaon, Sawargaon, Devi Babulgaon, Pothra, Palsingan, Mahajanwadi, Malwadi | Bid | Bid | Maharashtra | | Daradwadi, Khadewadi, Dakanwadi, Khomanwadi, Hangewadi, Nandur Ghat | Kaij | Bid | Maharashtra | | Dongarwadi, Singewadi, Para, Daulatabad, Fakrabad | Wasi | Usmanabad | Maharashtra | Now, after careful consideration, Ministry of Power, Government of India, under section 164 of the Electricity Act, 2003, confers all the powers to M/s Torrent Solar Power Private Limited for laying above overhead transmission line, which telegraph authority possesses under the Indian Telegraph Act, 1885 with respect to placing of telegraph lines and posts for the purposes of a telegraph established or maintained, by Government or to be established or maintained subject to following terms and conditions for installing the above mentioned line, namely: i. The approval is granted for 25 years. ii. The Applicant shall have to seek the consent of the concerned authorities i.e., local bodies, Railways, National Highways, State Highways etc. before erection of proposed line. iii. The Applicant shall have to follow regulations/codes of the Appropriate Commission regarding transmission, O&M, open access, etc., framed under the Electricity Act, 2003. iv. The Applicant shall operate the line after approval of Electrical Inspector / Chief Electrical Inspector of Central Government. v. The approval is subject to compliance of the requirement of the provisions of the Electricity Act, 2003 and the rules made there under by the applicant. vi. M/s Torrent Solar Power Private Limited shall have to submit the requisite clearances to Central Electricity Authority after obtaining the same from concerned authorities like Civil Aviation, Defense etc., at the time of Electrical Inspection. vii. In case, the route of above overhead lines (or some portion of the route of above overhead line) falls in the Great Indian Bustard (GIB) area, the applicant has to comply with the orders of the Hon’ble Supreme Court in the petition No.838 of 2019 regarding Great Indian Bustard (GIB) case, and the directions of the technical/expert committee constituted by the Hon’ble Supreme Court in this regard. [F. No. 25-16/37/2024-PG] M.V.N. VARA PRASAD, Under Secy. (PG) and Published by the Controller of Publications, Delhi-110054. SARVESH KUMAR SRIVASTAVA KUMAR SRIVASTAVA Date: 2024.10.07 21:58:29 +05'30'

Never miss important gazettes

Create a free account to save gazettes, add notes, and get email alerts for keywords you care about.

Sign Up Free